Completion of the foundations and reinforced concrete structures, prefabrication and assembly of the external steel trestle bridge as part of the “granular ammonium-nitrate-based fertiliser production plant” project

April-November 2016. GA Zakłady Azotowe Puławy in Puławy

SCOPE OF IMPLEMENTED WORK:

Construction of the foundations, reinforced concrete structures, structural grouts, earth electrodes, and protective pipe casings. Prefabrication of a steel structure with a total weight of 250 thousand kg. Protection of the structure against corrosion: shot blasting and spray painting. Assembly of steel structures.

Granulacja estakada
Completion of the foundations and reinforced concrete structures, prefabrication and assembly of the external steel trestle bridge
as part of the “granular ammonium-nitrate-based fertiliser production plant” project